<CMD><*1204
┌────────────────────────────────────────────────┐
│ TUTORIAL: Task list and PERT │
└────────────────────────────────────────────────┘
In this lesson you:
■ add task durations to the project, using
the Task list
■ add a new task to the project
■ see the results of your changes in the
PERT chart
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1204
This lesson uses the project you created in
the Work breakdown lesson. The Tutorial saved
that project in the PERT chart window.
When you get the project, it appears in
the window it was saved in -- the PERT chart.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1204
In this lesson you indicate how long each task
will take so HPM can begin calculating dates
and determine the project's length.
Also, the VP of Sales wants to take a look at
the plans for the booth. She needs to approve
them before construction gets under way, so you
need to add a task for approval.
───────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1216
To get a project, select ~Get/Save/Remove~2.
───────────────────────────────────────────────────
Type ~5~2><CMD>
<XFLD>5<XFLD><CMD><*1210
This is the Project list window. You start here
to get a project you've saved. Normally, you use
the Up and Down Arrow keys to move the cursor to
the project you want. Then you press Enter and
HPM gets the project and displays the window
where it was last saved.
───────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1214
But there's another way, too. You use that method
now. Start by pulling down the Files menu.
──────────────────────────────────────────────────
Press F2><CMD>
<XFLD><F2><XFLD><ENDDEF><CMD><*0414
Now select ~Get project~2
from the Files menu.
───────────────────────────
Press Enter><CMD>
<XFLD><ENTER><XFLD><ENDDEF><CMD><*0513
A fill-in appears. You
clear it first.
───────────────────────────
Press Ctrl-E><CMD>
<XFLD><CtrlE><XFLD><ENDDEF><CMD><*0513
Now you want to get the
project called HITECH.
───────────────────────────
Type ~HITECH~2><CMD>
<XFLD>HITECH<XFLD><ENDDEF><CMD><*0513
Now confirm it.
───────────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><F10><CMD><*1215
This is the window the project was last saved in.
You now want to display the Task list. Start by
pulling down the Data menu.
──────────────────────────────────────────────────
Press F3><CMD>
<XFLD><F3><XFLD><ENDDEF><CMD><*1215
The cursor is already on ~Task list~2, so just
select it.
──────────────────────────────────────────────────
Press Enter><CMD>
<XFLD><ENTER><XFLD><CHOME><DN><CMD><*1214
The Task list window overlays the PERT chart. At
this window you can add more tasks, change the
order of tasks, or include more information about
the tasks listed.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1214
Right now, you can't see all the columns in this
window. (Look for the arrow and the word ~More~2 in
the upper right corner of the screen.) Later you
move the cursor to see the other columns.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1214
The Task list shows the name of each task in the
first column. The second column shows the type of
task. An ~M~2 in this column means the task is a
special kind of task known as a ~milestone~2.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1213
A milestone is like a checkpoint that marks the
start or end of a series of tasks, or an important
point in the project such as the approval of plans.
It has no duration, so the ~Planned duration~2 column
for all milestones is blank.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1214
For tasks, the ~Planned duration~2 column shows
the default of zero. The ~Earliest start~2 column
shows the same date as the planned start for the
project until you add task durations.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1214
You entered the planned duration of Plan and
Build when you created them. Now you can enter
durations for the others. First find ~Recruit~2.
───────────────────────────────────────────────────
Press Ctrl-F><CMD>
<XFLD><CtrlF><XFLD><ENDDEF><CMD><*0516
Erase the fill-in.
──────────────────
Press Ctrl-E><CMD>
<XFLD><CtrlE><XFLD><ENDDEF><CMD><*0516
Type the name and confirm it.
─────────────────────────────
Type ~Recruit~2 and press F10><CMD>
<XFLD>Recruit<F10><XFLD><ENDDEF><CMD><*1216
Now move over to the ~Planned duration~2 column.
──────────────────────────────────────────────────
Press Tab twice><CMD>
<XFLD><TAB><TAB><XFLD><ENDDEF><CMD><*1216
It will take 5 working days to recruit the staff.
──────────────────────────────────────────────────
Type ~5~2 and press Enter><CMD>
<XFLD>5<ENTER><XFLD><ENDDEF><CMD><*1216
Before adding a duration for ~Train~2, take a look
at the ~Earliest start~2 column.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1215
After you add a task duration, HPM calculates the
earliest start dates for as many tasks as it can.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1215
If your project is large, calculations take time.
But HPM can suspend automatic calculations.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1215
To turn automatic calculations off temporarily,
pull down the ~Compute~2 menu.
──────────────────────────────────────────────────
Press F6><CMD>
<XFLD><F6><XFLD><ENDDEF><CMD><*1217
Select ~Calc on/off~2.
──────────────────────────────────────────────────
Press Enter><CMD>
<XFLD><ENTER><XFLD><ENDDEF><CMD><*1217
Change ~Automatic recalculation~2 to ~Off~2.
──────────────────────────────────────────────────
Press Right Arrow><CMD>
<XFLD><RGT><XFLD><ENDDEF><CMD><*1217
Confirm that the fill-in is complete.
──────────────────────────────────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><ENDDEF><CMD><*1215
Now, when you add durations, HPM will operate
faster. Now you can add a duration for training.
───────────────────────────────────────────────────
Press Ctrl-F><CMD>
<XFLD><CtrlF><XFLD><ENDDEF><CMD><*0516
Erase the fill-in.
──────────────────
Press Ctrl-E><CMD>
<XFLD><CtrlE><XFLD><ENDDEF><CMD><*0516
Type the name and confirm it.
─────────────────────────────
Type ~Train~2 and press F10><CMD>
<XFLD>Train<F10><XFLD><ENDDEF><CMD><*1216
Now move over to the ~Planned duration~2 column.
──────────────────────────────────────────────────
Press Tab twice><CMD>
<XFLD><TAB><TAB><XFLD><ENDDEF><CMD><*1216
It takes 5 working days to train the staff for
the booth at the HiTech Expo.
──────────────────────────────────────────────────
Type ~5~2 and press Enter><CMD>
<XFLD>5<ENTER><XFLD><ENDDEF><CMD><*1215
Before adding another duration, look at the bottom
line of the screen for the words ~Needs Calc~2.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1214
Whenever you turn off automatic calculations and
make a change that requires a calculation, HPM
displays this reminder. You can recalculate the
project when you're done adding task information.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1214
Now add a duration to ~Materials~2.
───────────────────────────────────────────────────
Press Ctrl-F><CMD>
<XFLD><CtrlF><XFLD><ENDDEF><CMD><*0516
Erase the fill-in.
──────────────────
Press Ctrl-E><CMD>
<XFLD><CtrlE><XFLD><ENDDEF><CMD><*0416
Type the name and confirm it.
─────────────────────────────
Type ~Materials~2. Press F10.><CMD>
<XFLD>Materials<F10><XFLD><ENDDEF><CMD><*1216
Now move over to the ~Planned duration~2 column.
──────────────────────────────────────────────────
Press Tab twice><CMD>
<XFLD><TAB><TAB><XFLD><ENDDEF><CMD><*1216
Supplying the necessary Sales materials for the
booth is expected to take 10 working days.
──────────────────────────────────────────────────
Type ~10.0~2><CMD>
<XFLD>10.0<XFLD><ENDDEF><CMD><*1216
Now you need to add a task for the VP's approval.
Start by moving the cursor to the bottom line.
──────────────────────────────────────────────────
Press Ctrl-End><CMD>
<XFLD><CtrlEND><XFLD><ENDDEF><CMD><*1205
Move down to the new line.
─────────────────────────────
Press Down Arrow><CMD>
<XFLD><DN><XFLD><ENDDEF><CMD><*1205
Now type your new task name.
─────────────────────────────
Type ~Approval~2><CMD>
<XFLD>Approval<XFLD><ENDDEF><CMD><*1205
Approval of the plan is a milestone.
────────────────────────────────────
Press Tab and type ~M~2><CMD>
<XFLD><TAB>M<XFLD><ENDDEF><CMD><*1205
Move the cursor past the next two columns.
──────────────────────────────────────────
Press Tab three times><CMD>
<XFLD><TAB><TAB><TAB><XFLD><ENDDEF><CMD><*1205
As you move the cursor across the window, new
columns come into view. But HPM always displays
the first two columns, ~Name~2 and ~Type~2.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1205
You are responsible for seeing that the plan is
approved.
──────────────────────────────────────────────────
Type ~SalesMgr~2><CMD>
<XFLD>SalesMgr<XFLD><ENDDEF><CMD><*1205
You could also add a description, but for now,
just tell HPM that you're done.
──────────────────────────────────────────────────
Press Enter><CMD>
<XFLD><ENTER><XFLD><ENDDEF><CMD><*1205
When you add a task at the Task list, HPM displays
this fill-in so you can tell it where to place it.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1205
HPM supplies task names for the ~Add after~2 and
~Add before~2 fields.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1205
In this case, HPM's "guess" is ~after~2 Staff End
and ~before~2 a branch. You want to place it just
before End. Move to the Add before field.
──────────────────────────────────────────────────
Press Tab><CMD>
<XFLD><TAB><XFLD><ENDDEF><CMD><*1205
Now you see by the name column pointer that that
branch was right before ~End~2. Just confirm it.
──────────────────────────────────────────────────
Press F10><CMD>
<XFLD><F10><XFLD><CMD><*1205
Because you've made all the changes necessary,
you can now ask HPM to calculate dates. Use
the speed key for calculating.
──────────────────────────────────────────────────
Press Ctrl-C><CMD>
<XFLD><CtrlC><XFLD><ENDDEF><CMD><*1215
HPM takes a moment to calculate the project
dates and display them in the ~Earliest start~2
column. And the ~Needs Calc~2 reminder disappears.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1215
Now take a look at how these changes appear when
converted to a PERT chart.
──────────────────────────────────────────────────
Press Esc><CMD>
<XFLD><ESC><XFLD><CHOME><CMD><*1216
HPM has added a duration under each task.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1215
Each milestone now has a date associated with it.
Next you'll see HPM's calculated completion date.
──────────────────────────────────────────────────
Press End><CMD>
<XFLD><END><XFLD><CMD><*4413
You see the ~Approval~2
task and your project's
ending date. Now try
HPM's zoom capability.
────────────────────────
Press Ctrl-Z><CMD>
<XFLD><CtrlZ><XFLD><ENDDEF><CMD><*1215
The PERT chart's size shrinks to half-size. Now
move to the start to see the whole project.
──────────────────────────────────────────────────
Press the Home key><CMD>
<XFLD><HOME><XFLD><ENDDEF><CMD><*1215
Now use the zoom speed key again--for Full zoom.
──────────────────────────────────────────────────
Press Ctrl-Z><CMD>
<XFLD><CtrlZ><XFLD><ENDDEF><CMD><*1215
The third time you use it, you have moved through
all three zoom levels. Return to normal size.
──────────────────────────────────────────────────
Press Ctrl-Z><CMD>
<XFLD><CtrlZ><XFLD><ENDDEF><CMD><*1215
That's enough for this lesson.
──────────────────────────────────────────────────
Press Esc><CMD>
<XFLD><ESC><XFLD><CMD><*1218
Before returning to the Tutorial menu, take a
minute to review the lesson.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF><CMD><*1204
~In summary ...~2
■ Use the ~Task list~2 to add tasks and
planned durations to your project.
■ To accelerate HPM's operation, turn
off automatic calculations.
■ Use ~Ctrl-C~2 whenever you want HPM
to calculate your changes.
■ For a quick overview of the dates of
milestones or the durations of tasks,
switch to the PERT chart.
──────────────────────────────────────────────────
Press Space bar><CMD>
<XFLD><Ctrl5><XFLD><ENDDEF>